Eligibility to seek Open Access (OA)
|
- A licensee or a generating company or a captive generating plant or a consumer or any person engaged in the business of supplying electricity to the public or any other person on payment of charges.
- Any person intending to avail open access must have a valid connectivity agreement with the concerned licensee as per the state electricity grid code.
- Persons intending to have open access connections must have ABT compliant meters as per CEA (Installation and Operation of Meters) Regulations, 2006, as amended from time to time.
|
Criterion for Granting Open Access
|
- Following factors are considered for granting open access:
- Load flows anticipated at assessed output from the generating station considering transmission planning criteria.
- Maximum load on such transmission and associated system recorded during the previous year viz-a-viz safe capacity of such a system.
- Appropriate load growth potential.
- Additional investment planning on new lines or improvement in lines.
- Capacity already allotted for the relevant period.
- Evacuation network from on-going generating projects.
- Network augmentation/reorganization plan.
- Other essential factors.
|
Electricity Tariff
FY 2017-18
(Rs./KVA/Month)
|
Consumer Category
|
Demand Charge
|
Industry/Commercial/Public Utility.
|
384
|
Domestic (WBSEDCL).
|
35
|
Domestic (CESC).
|
26
|
Irrigation (WBSEDCL).
|
34
|
|
Nodal Agency
|
- STU – for long term and medium term open access within the state if STU’s system is used.
- Transmission or Distribution Licensee – in whose system the point of drawal of electricity is located in case STU system is not used.
- SLDC – for short term open access, open access for emergency requirement and trial run within the state.
- Distribution licensee – in case open access drawal or injection points are within the area of a single distribution licensee.
|
Application Charges
|
Type of Open Access
|
Up to 100 MW
|
Over 100 MW to 500 MW
|
Over 500 MW to 1000 MW
|
More than 1000 MW
|
LTOA
|
Rs.2 lakh
|
Rs.3 lakh
|
Rs.6 lakh
|
Rs.9 lakh
|
MTOA
|
Rs.1 lakh
|
Rs.2 lakh
|
Rs.3 lakh
|
Rs.4 lakh
|
STOA
|
Rs.5000 per application.
|
|
Procedure for Long Term Open Access (LTOA)
|
- For inter-state transmission system – as per Central Electricity Regulatory Commission.
- For intra-state transmission system and within the same distribution licensee’s system:
- Capacity assessment by concerned licensees.
- In case capacity strengthening is not required, consent of access shall be given within 30 days from the date of receipt of application.
- In case of ineligibility or further capacity strengthening requirement, decision shall be communicated within 30 days from receiving the application.
- Concerned licensee shall carry out system studies and preliminary investigation for the purpose of capacity strengthening within 60 days from receiving amount of expenditure following request from the applicant.
- System strengthening shall be done with advance payment from the applicant, which will be repaid in installments.
- In case strengthening is required in inter-state transmission system to absorb/evacuate power beyond intra-state transmission system, the applicant shall coordinate with concerned utility.
|
Procedure for Medium Term Open Access (MTOA)
|
- For inter-state transmission system – as per Central Electricity Regulatory Commission.
- For intra-state transmission system and within the same distribution licensee’s system:
- To be granted if the resultant power flow can be accommodated in the transmission/distribution system.
- No augmentation of transmission/distribution system unless mutually decided by the applicant and the licensee.
- Construction of dedicated line shall not be construed as the augmentation of transmission/distribution system.
- In case MTOA can be allowed, consent for the same should be given within 30 days from the date of receipt of application.
- In case MTOA cannot be allowed, decision of disallowing MTOA shall be communicated within 30 days of receipt of application.
|
Procedure for Short Term Open Access (STOA)
|
- For inter-state transmission system – as per Central Electricity Regulatory Commission.
- For intra-state transmission system and within the same distribution licensee’s system:
- Separate application shall be made for each month and each transaction in the month.
- Application up to the fourth month including the month of application may be made.
- No provision for system strengthening unless mutually agreed by the applicant and the licensee.
- Advance Reservation – Application received up to the 19thday of the Nth month for OA commencing and terminating in the (N+1)th or (N+2)th or (N+3)rd month shall be treated as advance application.
- In case no congestion or technical limitations are anticipated STOA shall be granted for the quantum and duration sought for in the application.
- In case probable congestion or technical limitations are anticipated and communicated to the applicant, the applicant may reduce its requirement or opt for STOA for a period during which no congestion is anticipated.
- Even after that, if congestion is anticipated, then the reservation of transmission or wheeling capacity shall be made pro rata to the transmission or wheeling capacity reservation sought for.
- First come first served basis – for applications received for OA in the month in which the application is made or after 19thof a month for OA commencing and terminating in the following month.
- Applications should reach the nodal agency at least 4 days in advance from the date of commencement of STOA.
- Applications received up to 5 pm on a particular day shall be considered to be received on that day.
- Day ahead transaction – for applications received within three days of commencement of open access.
- Same day transactions – for short term energy requirements on the same day as the application and shall be accommodated to the extent practically possible.
|