Renewable Energy
Find latest News, Industry Updates, Markets, Finance, Policies and Regulations, Tenders
HIGHLIGHTS |
Eligibility to seek Open Access (OA) |
| |||||
Electricity Tariff FY 2017-18 for HT industry (Rs./kVAh) | Category | Load Factor | Energy Charges (Rs./kVAh) | |||
Contract load up to 1000 kVA | Up to 40% | 3.65 | ||||
Above 40% | 4.00 | |||||
Contract load above 1000 kVA | Up to 40% | 3.65 | ||||
Above 40% | 4.00 | |||||
Connectivity Charges and Procedure |
For Connectivity at Intra-state Transmission System:
For Connectivity at Distribution System:
For Connectivity to the distribution system by a consumer of a distribution licensee: As per the UERC (Release of new HT and EHT Connections, Enhancements and Reduction of Loads) Regulations, 2008. | |||||
Nodal Agency | -As per table below- | |||||
Procedure and Charges for Long Term Open Access (LTOA) |
| |||||
Location of Injection and Drawal Point | Nodal Agency | Application Fee | Time Frame for Processing the Application | |||
Both within the area of the same distribution licensee area. | Distribution Licensee | Rs.50,000 | 20 days | |||
Drawal point in distribution system – injection in intra-state transmission (and vice-versa), both in intra-state transmission. | STU | Rs.2,00,000 | 120 days where system augmentation is not required. Where augmentation is required – 270 days for transmission system and 180 days for distribution system. | |||
| ||||||
Procedure and Charges for Medium Term Open Access (MTOA) |
| |||||
Location of Injection and Drawal Point | Nodal Agency | Application Fee | Time Frame for Processing the Application | |||
Both within the area of the same distribution licensee area | Distribution Licensee | Rs.50,000 | 20 days | |||
Drawal point in distribution system – injection in intra-state transmission system (and vice-versa). | STU | Rs.1,00,000 | 40 days | |||
Both in intra-state transmission system. | 20 days | |||||
Start date of MTOA shall not be earlier than 5 months and not later than 1 year from the last day of the month in which the application was made. | ||||||
Procedure and Charges for Short Term Open Access (STOA) |
| |||||
Location of Injection and Drawal Point | Nodal Agency | Application fee | Time Frame for Processing the Application | |||
Both within the area of the same distribution agency. | Distribution Licensee | Rs.2000 | 7 working days, if applying for the first time, else 3 working days. | |||
Drawal Point in distribution system – injection in intra-state transmission system (and vice-versa). Both in intra-state transmission system. | SLDC | Rs.5000 | ||||
Without involving Inter-state Transmission System:
|
OTHER PROVISIONS |
Allotment priority |
|
Open Access Charges | Transmission Charges:
Cross Subsidy Surcharge:
Wheeling Charges:
|
Scheduling and Metering | Scheduling:
Metering:
|
Energy losses | Transmission Losses:
Distribution Losses
|
Imbalance/ Deviation and Reactive Energy Charges | Deviation Energy Charges:
§ In case of over-drawal – deviation charges payable are equal to average billing rate of HT industrial. § In case of under-drawal – deviation charges payable by distribution licensee are equal to the average power purchase cost of the distribution licensee.
· When OA consumer is not a consumer of distribution licensee: § In case of over-drawal – deviation charges payable to licensee as per the applicable tariff. If demand exceeds, then additional excess demand charges shall be paid. § In case of under-drawal – consumer shall be compensated at the rate of average power purchase cost.
§ Under-injection due to licensee’s problem and over-injection – deviation charges payable by licensee to generator at APPC. § Under-injection due to generator’s problem – deviation charges payable by generator to licensee at APPC.
Reactive Energy Charges:
|
Link | |
References | UERC (Terms & Conditions of Intra State Open Access) Regulations, 2015 http://www.uerc.gov.in/Rules%20and%20regulation/UERCRegulations/Regulations,%202015/Open%20Access%20Regulations,%202015/UERC%20 Uttarakhand Electricity Regulatory Commission (Terms and Conditions of Intra-State Open Access) (First Amendment) Regulations, 2016. http://www.uerc.gov.in/Rules%20and%20regulation/UERCRegulations/Regulations%202016/UERC%20Open%20Access%20Amendment UPCL (Distribution) Tariff Order 2017-18:
PTCUL (Transmission) Tariff Order 2017-18:
SLDC Tariff Order 2017-18: |
About Portal
'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More
About
Useful Links
Contact
Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India
+91 20 26613855
+91 20 26613832