Renewable Energy
Find latest News, Industry Updates, Markets, Finance, Policies and Regulations, Tenders
HIGHLIGHTS |
Technology-wise Net Tariff
| Technology | Net Tariff (Rs./kWh) | |
Wind (Jaisalmer, Barmer, Jodhpur) | 5.16 | ||
Wind (other than Jaisalmer, Barmer, Jodhpur) | 5.42 | ||
Solar PV | 4.85 | ||
Solar thermal | 10.34 | ||
Biomass with water-cooled condenser | 6.83* | ||
Biomass with air-cooled condenser | 7.41* | ||
Biogas | 7.84* | ||
Biomass gasifier | 6.67* | ||
*Without availing Accelerated Depreciation | |||
Project developer can opt for project-specific tariff for the following:
| |||
Tariff Period
| Technology | No. of Years | |
Wind, Solar PV, Solar thermal | 25 | ||
Biomass, Biomass gasifier, Biogas | 20 | ||
Control Period
|
| ||
Useful Life of a Plant
| Technology | No. of Years | |
Wind, Solar PV, Solar thermal | 25 | ||
Biomass, Biomass gasifier, Biogas | 20 | ||
Capital Cost
| Technology | Rs. Lakh/MW | |
Wind | 579.84 | ||
Solar PV | 518.59 | ||
Solar thermal | 1182.30 | ||
Biomass with water-cooled condenser | 527.78 | ||
Biomass with air-cooled condenser | 561.98 | ||
Biogas | 856.77$ | ||
Biomass gasifier | 443.49* | ||
*Subsidy of Rs.150 lakh/MW $Subsidy of Rs.300 lakh/MW | |||
Operation and Maintenance (O&M) Expenses
| Technology | Rs. Lakh/MW | |
Wind | 8.82 | ||
Solar PV | 7.00 | ||
Solar thermal | 18.79 | ||
Biomass with water-cooled condenser | 42.27 | ||
Biomass with air-cooled condenser | 45.07 | ||
Biogas | 56.06 | ||
Biomass gasifier | 56.06 | ||
The escalation in O&M is 5.85% per annum. | |||
Interest Rate on Loans | 12.76% | ||
Depreciation
|
| ||
Return on Equity
|
| ||
Interest on Working Capital
|
| ||
Banking of Energy for Biogas and Biomass | Extra energy fed into the grid will be compensated at 60% of energy charges for the industrial customer. | ||
OTHER PROVISIONS |
Tariff Structure and Design | Single part, levelised tariff.
|
Despatch Principle | ‘MUST RUN’ plants and hence not subject to merit order despatch principle. |
Subsidy or/and Incentives by Government | Any incentive or subsidy provided by the central or state government including accelerated depreciation benefit. |
Rebate
|
|
Late Payment Surcharge | 1.25% per month, on a daily basis, for payments beyond 45 days from date of presentation of bills. |
Links |
|
References
| http://rerc.rajasthan.gov.in/Regulations/Reg87.pdf
http://rerc.rajasthan.gov.in/Regulations/Reg79.pdf
http://rerc.rajasthan.gov.in/TariffOrders/Order239.pdf
http://rerc.rajasthan.gov.in/TariffOrders/Order249.pdf
http://rerc.rajasthan.gov.in/TariffOrders/Order248.pdf
http://rerc.rajasthan.gov.in/Regulations/Reg85.pdf
http://rerc.rajasthan.gov.in/Regulations/Reg114.pdf
http://rerc.rajasthan.gov.in/TariffOrders/Order304.pdf
https://rerc.rajasthan.gov.in/rerc-user-files/regulations (1st amendment)
|
About Portal
'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More
About
Useful Links
Contact
Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India
+91 20 26613855
+91 20 26613832