Control Period | From date of publication in the official gazette. |
Eligibility Condition |
|
Capacity Target for Distribution Licensee | Cumulative capacity of solar rooftop system should not exceed 30% of the rated capacity of the concerned distribution transformer. |
Metering | The solar meter should be installed at the point at which the electricity is generated by solar energy system and delivered at the main panel. |
OTHER PROVISIONS |
Energy accounting and settlement |
|
Other charges | Exempted from PSERC (Terms and Conditions for Intra-state Open Access) Regulations 2011. |
Penalty | In case of failure, provisions of Supply Code shall apply. |
Link | |
Reference | http://mnre.gov.in/file-manager/Compendium/Final/Punjab%202.pdf |
About Portal
'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More
About
Useful Links
Contact
Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India
+91 20 26613855
+91 20 26613832