Odisha Renewable Power Purchase Obligation and its Compliance Regulations, 2015

  • / /

HIGHLIGHTS

 

Control Period

From September 10, 2015.

Renewable Purchase Obligation (RPO)

Year

Minimum quantum of purchase (in %) from renewable energy sources (in terms of energy equivalent in kWh)

Solar

Non-solar

Total

2016-17

1.50

3.00

4.50

2017-18

3.00

4.50

7.50

2018-19

4.50

5.00

9.50

2019-20

5.50

5.50

11.00

  • Renewable power purchase under power purchase agreements already entered into shall continue to be made till their present validity.
  • Compliance (FY 2015-16)-20.50%

Obligated Entities

  • Distribution licensee or any other entity procuring power on their behalf.
  • Any person consuming electricity:
    • generated from conventional captive generating plant having capacity of 1MW and above for his own use

or

    • procured from conventional generation through open access and third party sale.

Ways to Meet RPO

Options for “obligated entity” to meet RPO target:

  • from its own renewable sources
  • by procurement of power from other developers of RE sources
  • by purchase from other licensees
  • by way of purchase of REC 

Certificates

  • Obligations to purchase solar and non-solar energy can be fulfilled by purchase of solar and non-solar certificates,respectively. In case no solar certificatesare available for the year, additional non-solar certificates should be purchased for fulfilment of RPO.
  • Certificates purchased by obligated entities shall be deposited with the state agency in accordance with the detailed procedure laid down by the Central Agency. 

HIGHLIGHTS

 

State Agency

Odisha Renewable Energy Development Agency 

Effect of Default

  • The Commission may direct obligated entities to deposit a penalty to a separate fund created and maintained by the state agency in case of non-fulfilment of RPO and non-purchase of RECs.
  • Amount of penalty would be decided by the Commission based on the shortfall in units of RPO and the forbearance price as decided by the Central Commission.  

Monitoring and Implementation Framework

Not available

Links

http://www.orierc.org/regulations.html

References

http://www.orierc.org/Gazette%201301-2015.pdf

 

 

About Portal

'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More

Contact

Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India

+91 20 26613855
+91 20 26613832