Maharashtra Electricity Regulatory Commission (Forecasting, Scheduling, Deviation Settlement for Solar and Wind Generation Sources) Regulations, 2018

  • / /

HIGHLIGHTS

 

Eligible Entities

  • All wind and solar energy generators with individual or combined capacity of 5 MW and above connected to the state grid independently or through pooling station.
  • All wind and solar generators of any capacity connected to the state grid through pooling stations with total capacity of 5 MW and above.

 

Forecasting & Scheduling

  • Qualified Coordinating Agency (QCA) shall provide day-ahead and week-ahead schedule to the SLDC.
  • Day-ahead schedule: At intervals of 15 minutes for the next day, starting from 00:00 hours of that day.
  • Week-ahead schedule: At intervals of 15 minutes for the next seven days, starting from 00:00 hours of the day.
    • Revision can be done by giving notice effective from the 4th time block – the 1st being when notice was given.
    • One revision for each one-and-a-half-hour time block subject to a maximum of 16 revisions in a day.

 

Role of QCA and Implementation

  • One QCA for each pooling sub-station or generating station registered with SLDC.
  • QCA shall be the single point of contact with respect to:

 

  • Meter reading, data collection and its communication.
  • QCA shall furnish technical specification and also provide real time data to connected SLDC.
  • Coordination between distribution licensee, SLDC and other agencies.
  • Commercial settlements between generators and their counterparties.
  • All other ancillary or incidental matters.

 

Commercial and Deviation Settlement

  • Generators connected to the state grid and selling power within the state, to be paid as per actual generation.
  • Generators connected to the state grid and selling power outside the state, to be paid as per scheduled generation.
  • Deviation settlement for regional entities will be according to the Central Electricity Regulatory Commission (Deviation Settlement Mechanism and Related Matters) Regulations, 2018, as amended from time to time.

 

 

 

OTHER PROVISIONS

 

Deviation Charges for Sale of Power within the State

Under or over injection (for plants commissioned before the date of notification):

Absolute Error in a 15-min. time block

Deviation Charges payable to State DSM Pool

≤15%

None.

>15% but ≤ 25%

At Rs.0.50 per unit.

>25% but ≤35%

At Rs.0.50 per unit for the shortfall or excess beyond 15% and up to 25% + Rs.1.00 per unit for balance energy beyond 25% and up to 35%.

>35%

At Rs.0.50 per unit for the shortfall or excess beyond 15% and up to 25% + Rs.1.00 per unit for balance energy beyond 25% and up to 35% + Rs.1.50 per unit for balance energy beyond 35%.

 

Payment Mechanism

  • Deviation charges shall be paid within ten days from date of issue by SLDC.
  • Late payment will attract surcharge of 1.25 % per month.

 

Energy Accounting

  • SLDC shall furnish data on weekly basis through IT enabled system and software.

Metering

  • Metering to record parameters in every 15 minute time block.
  • QCA shall furnish weekly meter readings to SLDC by 00:00 hours on Thursday of the previous week.
  • Data telemetry shall be adopted at the turbine/inverter or plant level as considered appropriate by SLDC.

 

Link

https://www.merc.gov.in/

 

 

Reference

https://www.merc.gov.in/faces/merc/common/outputClient.xhtml

 

 

 

About Portal

'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More

Contact

Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India

+91 20 26613855
+91 20 26613832