Control Period | From the date of notification in official Gazette
|
Eligibility Condition |
|
Capacity Target for Distribution Licensee | Cumulative solar energy capacity should not exceed 65% of the peak capacity of the distribution transformer.
|
Metering Arrangement |
|
RPO compliance |
|
OTHER PROVISIONS |
Energy Accounting and Settlement |
|
Other Charges | Exempted from transmission and wheeling charges and losses, cross subsidy surcharge and additional surcharge.
|
Penalty | Penalty or compensation shall be payable as per the provisions of the GERC (Standard of Performance of Distribution Licensee) Regulations, 2005 as amended from time to time.
|
Link | http://www.gercin.org/regulations.aspx
|
Reference | http://www.gercin.org/uploaded/document/adf57eac-f111-4b33-b447-b07ecaa34165.pdf http://demo.gercin.org/uploaded/document/f96a77e1-0e98-4d93-94a6-19c9d14ba333.pdf http://demo.gercin.org/uploaded/document/0862119c-4f94-40ab-b6c5-7cfefa2309b6.pdf
|
*As per Gujarat Electricity Regulatory Commission (Net Metering Roof Top Solar PV Grid Interactive Systems) (Second Amendment) Regulations, 2020
About Portal
'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More
About
Useful Links
Contact
Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India
+91 20 26613855
+91 20 26613832