Renewable Energy
Find latest News, Industry Updates, Markets, Finance, Policies and Regulations, Tenders
HIGHLIGHTS |
Eligibility to seek Open Access |
| ||||
Electricity Tariff (2017-18) (Rs./Unit) | UGVCL, DGVCL, PGVCL, MGVCL | ||||
HTP1 upto 500kVA | 4.00 | ||||
HTP1 500-2500kVA | 4.20 | ||||
HTP1 2500+ kVA | 4.30 | ||||
Connectivity charges and procedure | Intra-state transmission system
| ||||
Quantum of power to be injected/off take into/from Intra-State Transmission and/or Distribution System | Application fee for renewable sources connectivity (Rs. lakhs) | ||||
Up to 100 MW | 2 | ||||
100 – 500MW | 3 | ||||
500 – 100 MW | 6 | ||||
More than 1000 MW | 9 | ||||
Distribution System
| |||||
Nodal Agency | - As per the table below- | ||||
Procedure and Charges for Long-Term Open Access |
| ||||
Location of Injection and Drawal Point | Nodal Agency | Application Fee | Time Frame for Processing the Application | ||
Consumer Connected to Distribution System | |||||
Both within the same distribution licensee area | SLDC | Rs.25,000 | 30 days | ||
Both within the state but with different licensees.Injection at intrastate transmission system. | STU | Rs.50,000 | 120 days where systemaugmentation is not required. 150 days where required. | ||
Consumer Connected to Transmission System | |||||
Both within the intra-state transmission system.Injection point in distribution system within the state. | STU | Rs.50,000 (upto 100MW) Rs.1,00,000 above 100 MW | 120 days where systemaugmentation is not required. 150 days where required. | ||
Bank guarantee at the rate of Rs.10,000 (Rupees Ten thousand only) per MW in favour of nodal agency. | |||||
Procedure and Charges for Medium-Term Open Access |
| ||||
Location of Injection and Drawal Point | Nodal Agency | Application Fee | Time Frame for Processing the Application | ||
Consumer Connected to Distribution System | |||||
Both within the same distribution licensee area | SLDC | Rs.25,000 | 30 days | ||
Both within the state but with different licensees. Injection at intra-state transmission system within the state. | STU | Rs.50,000 | 40 days | ||
Consumer Connected to Transmission System | |||||
Both within intra-state transmission system (Gujarat). Injection point within distribution system within Gujarat. | STU | Rs.25,000 (capacity upto 100 MW) Rs.50,000 (for more) | 30 days | ||
Procedure and Charges for Short-Term Open Access |
| ||||
Location of Injection and Drawal Point | Nodal Agency | Application fee | Time Frame for Processing the Application | ||
Consumer Connected to Distribution System | |||||
Both within the same distribution licensee area | SLDC | Rs.2000
| For OA in Advance: As latest by 21st day of such preceding month , while application is upto 15th day of preceding month. For Day ahead open access: Application to be submitted upto 1300 of the preceding day. Nodal agency shall convey acceptance or rejection accordingly. | ||
Both within Gujarat but having different distribution licenseesareas. Injection point in intra-state transmission system. | SLDC | Rs.5000 | |||
Consumer Connected to Transmission System | |||||
Both connected to intra-state transmission system. Injection point within distribution network in the state | SLDC | Rs.5000 | For OA in Advance: As latest by 21st day of such preceding month , while application is upto 15th day of preceding month.
For Day ahead open access: Application to be submitted upto 1300 of the preceding day. Nodal agency shall convey acceptance or rejection accordingly. |
OTHER PROVISIONS |
Allotment priority |
| ||
Open access charges (FY 2017-18) |
Transmission Charges:
Cross Subsidy Surcharge and Additional Surcharge:
Wheeling charges
| ||
Scheduling, Metering | Scheduling
Metering
| ||
Energy losses | Transmission Losses (17-18)
Distribution Loss (17-18) :
| ||
Point of Energy Delivered | |||
Point of Injection | 11kV | 400V | |
11kV, 22kV, 33kV | 10% | 14.24% | |
400V | -- | 7.01% | |
Imbalance and Reactive energy charges | Imbalance Energy
Reactive energy charges:
| ||
Link | |||
Reference | GERC Intra State Open Access Regulations 2011: http://www.gercin.org/uploaded/document/en_1307189397.pdf GERC Multi Year Tariff regulations 2016:http://www.gercin.org/uploaded/document/32cce6db-6f9d-4a69-9b8a-62255e00cc20.pdf Amendment 2_GERC OA_2014: http://www.gercin.org/uploaded/document/en_1408010427.pdf SLDC Tariff Order (17-18) : http://www.gercin.org/uploaded/document/d609858b-57e8-4912-ac0d-0c33d3de2d73.pdf UGVCL (Tariff Order 17-18) : http://www.gercin.org/uploaded/document/53b22956-8e4e-4ce1-b6b3-b65283c8fed3.pdf GETCO (Tariff Order 17-18) : http://www.gercin.org/uploaded/document/9940633e-fd42-4ea9-8d35-c2f2abfd7bdd.pdf GSECL (Tariff Order 17-18) : http://www.gercin.org/uploaded/document/edb78b56-055e-400a-9667-8d7d6e49e60e.pdf DGVCL (Distribution Tariff Order 17-18) : http://www.gercin.org/uploaded/document/cf45259d-bc47-4ba6-b124-7a2217a85801.pdf MGVCL (Distribution Tariff Order 17-18) : http://www.gercin.org/uploaded/document/f498d841-23f1-4b03-a3a2-244b2d813e4b.pdf PGVCL (Distribution Tariff Order 17-18) : http://www.gercin.org/uploaded/document/9388701b-a52d-45e3-a50c-c73a67acfd68.pdf |
About Portal
'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More
About
Useful Links
Contact
Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India
+91 20 26613855
+91 20 26613832