Tariff Period | 13 years for projects having COD after April 1, 2017. 5 years for projects having COD before April 1, 2012. | ||
Control Period | April 1, 2017 to March 31, 2020. | ||
Useful Life of a Plant | Technology | No. of Years | |
Non-fossil fuel based cogeneration, biomass based on Rankine cycle, MSW/RDF | 20 | ||
Wind, solar PV, solar thermal | 25 | ||
Small hydro | 35 | ||
Technology-wise net Tariff | Not Available | ||
Capital Cost | Technology | Capital Cost (Rs.lakhs/MW)* | |
Wind | Project specific | ||
Small hydro below 5 MW | 779† | ||
Small hydro (5 MW to 25 MW) | 707† | ||
Biomass based on Rankine cycle technology | Project specific | ||
Non-fossil fuel cogeneration | 492.5 | ||
Solar PV | Project specific | ||
Solar thermal | Project specific | ||
MSW/RDF | Project specific | ||
† Capital cost is for FY 2017-18. Capital cost for subsequent years for projects to be commissioned in each subsequent year shall be as per central commission's notification/order. For small hydro projects, solar PV projects capital cost for plants commissioned before April 1, 2012 will be governed through respective approved orders of the commission. | |||
Operation and Maintenance (O&M) Expenses | Technology | O&M Cost (Rs.lakhs/MW)* | |
Wind | Project specific | ||
Small hydro below 5 MW | 29 | ||
Small hydro (5 MW to 25 MW) | 21 | ||
Biomass based on Rankine cycle | 40 | ||
Non-fossil fuel cogeneration | 21.13 | ||
Solar PV | Project specific | ||
Solar thermal | Project specific | ||
MSW/RDF | Project specific | ||
*O&M costs for small hydro, biomass and non-fossil fuel based cogeneration are for FY 2017-18.
| |||
Interest Rate on Loans |
| ||
Depreciation | 5.28% for first 13 years and remaining depreciation spread over residual useful life of the project. | ||
Return on Equity |
| ||
Interest on Working Capital | Equivalent to state bank of India marginal cost of funds based lending rate (one year tenor) prevalent on October 1st of the previous year plus 300 basis points. |
OTHER PROVISIONS |
Tariff structure and design | Generic,levellised, single part tariff for the tariff period. |
Merit Order Despatch Principle |
|
Subsidy or/and Incentives by central or state government | Any incentive or subsidy provided by the central or state government, including accelerated depreciation benefit, would be taken into consideration for determination of project specific tariff. |
Rebate |
|
Late payment surcharge | 1.25% per month for payment of bills beyond 60 days from the date of billing. |
Links | http://cserc.gov.in/regulations.php?r_type=Draft
|
References | http://cserc.gov.in/admin/upload_regulation/071117_063652_.pdf
|
About Portal
'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More
About
Useful Links
Contact
Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India
+91 20 26613855
+91 20 26613832