Eligibility to Seek Open Access | To the transmission and/or distribution system against payment of appropriate charges:
| ||
Electricity Tariff (FY 2018-19)
| Category | Fixed Charge (Rs./kW/ month or Rs./kVA/month) | Energy Charge (Rs./kWh) |
HT – I (11 kV) | 300 | 6.65 | |
HT – II (33 kV) | 300 | 6.60 | |
| |||
Criteria for Granting Access |
| ||
Connectivity |
| ||
Nodal Agency | Connection Type | Location of Injection and Drawal | Agency |
Consumer connected to distribution licensee | Both within the same distribution licensee’s area (STOA, MTOA, LTOA). | Concerned distribution licensee. | |
Both within the same state, but in the areas of different distribution licensees (STOA). | SLDC | ||
Injection point in the intra-state transmission system (STOA). | |||
Both within the same state, but in the areas of different distribution licensees (MTOA, LTOA). | STU | ||
Injection point in the intra-state transmission system (MTOA, LTOA). | |||
Both within the same state, but in the areas of different distribution licensees (LTOA). | |||
Injection point in the intra-state transmission system (LTOA). | |||
Both in different states (STOA). | Respective RLDC | ||
In different states (MTOA, LTOA). | CTU | ||
Consumer connected to intra-state transmission system | Both in the same state (STOA). | SLDC | |
Injection point in the distribution system within the state (STOA). | |||
In different states (STOA). | Respective RLDC | ||
Both in the same state (MTOA, LTOA). | STU | ||
Injection point in the distribution system within the state (MTOA, LTOA). | |||
In different states (MTOA, LTOA). | CTU | ||
| |||
Procedure and Charges for Long Term Open Access (LTOA) | As per Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium Term Open Access in Inter-state Transmission and related matters) Regulations, 2009 or its statutory re-enactments as amended from time to time involving inter-state transmission system. Application fees for consumers seeking connection to intra-state transmission system:
Application fees for consumers seeking connection to distribution system:
Application shall be accompanied by a bank guarantee corresponding to Rs.10,000/MW of the total power. Time frame for disposal of application for connection to intra-state transmission system:
Time frame for disposal of application for connection to distribution system:
| ||
Procedure and Charges for Medium Term Open Access (MTOA) | As per Central Electricity Regulatory Commission (Grant of Connectivity, Long Term Access and Medium Term Open Access in Inter-State Transmission and related matters) Regulations, 2009 or its statutory re-enactments as amended from time to time involving inter-state transmission system. Application fees for consumers seeking connection to intra-state transmission system:
Application fees for consumers seeking connection to distribution system:
Application shall be accompanied by a bank guarantee. Time frame for disposal of application for connection to the intra-state transmission system:
Time frame for disposal of application for connection to distribution system:
As per Central Commission’s Regulations in case drawal and injection points are in different states. | ||
Procedure and Charges for Short Term Open Access (STOA) | As per Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2008 or its statutory re-enactments as amended from time to time involving inter-state transmission system. Application fees for consumers seeking connection to intra-state transmission system:
Application fees for consumers seeking connection to distribution system – Rs.5,000 for all projects. Time frame for disposal of application for connection to intra-state transmission system:
Time frame for disposal of application for connection to distribution system:
Day-ahead open access applications should reach the nodal agency three days prior to the date of scheduling but no later than 13:00 hrs of the day immediately preceeding the day of scheduling. In case capacity sought exceeds availability or any congestion in the respective transmission and distribution system is found, then capacity shall be allocated through electronic bidding procedure. |
OTHER PROVISIONS |
Allotment Priority |
| ||
Open Access Charges | Category | NBPDCL/SBPDCL |
|
Transmission Charges | |||
STOA Consumers | Rs.0.51/kWh |
| |
Cross Subsidy Surcharge | |||
132 kV | Rs.1.71/kWh |
| |
33 kV (other than HTSS) | Rs.1.85/kWh |
| |
11 kV (other than HTSS) | Rs.1.87/kWh |
| |
HTSS (11 kV and 33 kV) | Rs.1.18/kWh |
| |
Wheeling Charges | |||
33 kV | Rs.0.27/ kWh |
| |
11 kV | Rs.0.31/ kWh |
| |
| |||
Scheduling and Metering | Scheduling
Metering
| ||
Energy Losses |
| ||
Reactive Energy Charges | Rs.0.04/kVAR | ||
Link | https://berc.co.in/publice-notice https://berc.co.in/orders/tariff/transmission | ||
References | https://berc.co.in/orders/tariff/distribution/sbpdcl/1444-tariff-order-of-sbpdcl-for-fy-2018-19 https://berc.co.in/orders/tariff/distribution/nbpdcl/1447-tariff-order-of-nbpdcl-for-fy-2018-19 |
About Portal
'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More
About
Useful Links
Contact
Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India
+91 20 26613855
+91 20 26613832