Tariff Period | 20 years from the date of commercial operation. | |
Control Period | April 1, 2016 – March 31, 2021 | |
Useful Life of a Plant | 20 years. | |
Net Tariff | Not available | |
Capital Cost | Technology | Capital Cost (Rs.lakhs/MW)* |
MSW to energy | 1575 | |
RDF to energy | 945 | |
| ||
Operation and Maintenance Expenses (O&M) | Technology | O&M Expenses (Rs lakhs/MW)* |
MSW to energy | 94.5 | |
RDF to energy | 56.5 | |
*O&M expenses are for FY 2016-17
| ||
Interest Rate on Loans | Average base rate of State Bank of India prevalent on October 1st of the previous year plus 300 basis points. | |
Depreciation |
| |
Return on Equity |
| |
Interest on Working Capital | Base rate of State Bank of India prevalent on 1st October of the previous year plus 350 basis points. |
OTHER PROVISIONS |
Tariff structure and design | Generic, levellised, single part tariff for the tariff period. |
Merit Order Despatch Principle | ‘Must run’ power plants and thereby not subject to scheduling and merit order dispatch principles. |
Subsidy or/and Incentives by central or state government |
|
Rebate |
|
Late payment surcharge | 1.25% per month for payment of bills beyond 60 days from the date of billing. |
Links | http://cserc.gov.in/regulations.php?r_type=Notified |
References | http://cserc.gov.in/admin/upload_regulation/060817_105300_.pdf |
About Portal
'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More
About
Useful Links
Contact
Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India
+91 20 26613855
+91 20 26613832