Eligibility to seek Open Access |
| ||
Electricity Tariff FY 2017-18 (Rs./kVAh) | Foe South Bihar PDCL and North Bihar PDCL | ||
HTS I – 11kV | 6.20 | ||
HTS II – 33 kV | 6.15 | ||
HTS III – 132kV | 6.10 | ||
HTS IV – 220 kV | 6.05 | ||
Connectivity Charges and Procedure | -Not Available - | ||
Nodal Agency |
| ||
Procedure and Charges for Long-Term Open Access |
| ||
Procedure and Charges for Medium-Term Open Access | -NA- | ||
Procedure and Charges for Short-Term Open Access |
| ||
Term of Open Access | Maximum Processing Time | ||
Up to one day | 12 hours | ||
Up to 7days | 2 days | ||
Up to 30 days | 7 days | ||
Up to 180 days | 15 days | ||
Up to one year | 30 days | ||
Non-utilization of energy: Capacity can be surrendered. Consumer shall bear the open access charges and all other charges (as applicable to STOA customers) on the full original allocated capacity for the remaining period of original allocation or till the time such capacity is allotted to some other customers. |
OTHER PROVISIONS |
Allotment priority |
| |||
Open access charges |
Transmission Charges
Cross Subsidy Surcharge (Tariff order 2017-18)
Wheeling Charges
Additional Surcharge
| |||
Scheduling and Metering | Scheduling
Metering
| |||
Energy losses |
| |||
Injection è | Transmission | 33kV | 11 kV | |
Drawal | ||||
Transmission | Transmission loss @ 3.92% | Transmission and wheeling cumulative loss @ 8.72%
| Transmission and wheeling loss for 33kV and 11 kV cumulative loss @ 14.20 % | |
33kV | Transmission and wheeling cumulative loss @ 8.72% | Wheeling losses of 33 kV network @ 5.00% | Wheeling losses of 33kV and 11 kV network. (Cumulative loss @ 10.70%) | |
11kV | Transmission and wheeling loss for 33kV and 11 KV cumulative loss @ 14.20% | Wheeling losses of 33kV and 11 kV network. Cumulative loss of 10.70% | Wheeling losses of 11 kV network @ 6.00%
| |
Imbalance and Reactive energy charges | Imbalance energy charges
Reactive energy charges
| |||
Link | http://berc.co.in/rules-requlations/regulations/individual-regulation | |||
References | The Bihar Electricity Regulatory Commission (Terms and Conditions for Open Access) Regulations, 2005: Southern Bihar Power Distribution Company Ltd ( Tariff Order 2017-18) http://berc.co.in/orders/tariff/distribution/sbpdcl/1142-tariff-order-of-sbpdcl-for-fy-2017-18 |
About Portal
'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More
About
Useful Links
Contact
Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India
+91 20 26613855
+91 20 26613832