Eligibility to seek Open Access (OA)

  • Generating companies, captive generating plants and consumers eligible against payment of requisite charges.
  • Capacities of 1 MW and above are eligible provided the Commission relaxes the capacity norms, subject to feasibility.
  • Limitation of 1 MW will not apply for power transmission to the place of its own use by a captive generator.

Criterion for Granting Open Access

  • Augmentation requirement of intra-state transmission system shall be duly considered before award of LTOA.
  • No augmentation of the transmission system will be granted to MTOA or STOA.
  • MTOA or STOA may be awarded if the resultant power flow can be accommodated in the existing transmission system or the transmission system under execution.
  • Construction of dedicated transmission lines are not to be construed as augmentation of the transmission system.

Electricity Tariff

FY 2016-17

(Rs./Unit)

Consumer Category

Tariff (Rs./Unit)

HTS – I

7.23

HTS – II

6.89

HTS – III

6.63

HTSS

6.89

Connectivity Charges and Procedure

Consumer Connected to Distribution System

Period

Inter-se location of drawal and injection points

Nodal Agency

Application fees (Rs.) for 10 MW and above

Application fees (Rs.) for less than 10 MW

Time frame for disposal of application (days from the receipt of application)

STOA

Both in the area of the same DISCOM.

Concerned DISCOM.

2000

2000

7 days for first application; 3 days for subsequent applications.

Both within the same state but with different DISCOMs.

SLDC

5000

5000

Injection point in the intra-state transmission system within the state.

SLDC

5000

5000

In different states.

NLDC or RLDC of the region where the consumer is located.

5000

5000

As per Central Commission’s regulations.

MTOA

Both in the area of the same distribution licensee.

Concerned distribution licensee.

50000

25000

20 working days.

Both in the same state, but with different distribution licensees.

STU

100000

50000

40 working days.

Injection point in the intra-state transmission system within the state.

STU

100000

50000

In different states.

CTU

100000

100000

As per Central Commission’s regulations.

LTOA

Both in the area of the same distribution licensee.

Concerned distribution licensee.

50000

25000

20 working days.

Both within the same state, but with different distribution licensees.

STU

100000

50000

120 days where augmentation is not required and 150 days where augmentation is required.

Injection point in the intra-state transmission system within the state.

STU

100000

50000

In different states.

CTU

100000

100000

As per Central Commission’s regulations.

Consumer Connected to Intra-State Transmission System

STOA

Both in the same state (in the intra-state transmission system).

SLDC

5000

5000

7 days for first application; 3 days for subsequent applications.

Injection point in the distribution system within the state.

SLDC

5000

5000

In different states.

NLDC or RLDC of the region where the consumer is located.

5000

5000

As per Central Commission’s regulations.

MTOA

Both within the same state (in the intra-state transmission system).

STU

100000

50000

20 working days.

Injection point in the distribution system within the state.

STU

100000

50000

20 working days.

In different states.

CTU

100000

100000

As per Central Commission’s regulations.

LTOA

Both within the same state (in the intra-state transmission system).

STU

200000

100000

120 days where augmentation is not required and 150 days where augmentation is required.

Injection point in the distribution system within the state.

STU

200000

100000

In different states.

CTU

200000

200000

As per Central Commission’s regulations.

 

Procedure and Charges for Long Term Open Access (LTOA)

  • Inter-state long term open access as per the Central Electricity Regulatory Commission (Grant of Connectivity, Long term Access and Medium-term Open Access in Inter-State Transmission and related matters) Regulations, 2009 or its statutory re-enactments, as amended from time to time.
  • Intra-state long term open access - Where augmentation of transmission system is required, the applicant shall also have to bear the transmission charges for the same.
  • Fresh application is required in case of change in location or change in quantum of power to be interchanged by more than 10 percent.
  • Application accompanied by non-refundable fee and bank guarantee of Rs.10,000 per MW of power to be transmitted.
  • Open access will be available no later than 5 days from the date of furnishing of agreements by the open access consumer.
  • LTOA may be extended on a written request by the consumer submitted to the STU at least six months prior to such expiry.  

Procedure and Charges for Medium Term Open Access (MTOA)

  • Inter-state medium term open access as per the Central Electricity Regulatory Commission (Grant of Connectivity, Long term Access and Medium-term Open Access in Inter-State Transmission and related matters) Regulations, 2009 or its statutory re-enactments, as amended from time to time.
  • Fresh application is required in case of change in location or change in quantum of power to be interchanged by more than 10 percent.
  • The start date of medium term open access shall not be earlier than 5 months and not later than 1 year from the last day of the month in which application has been made.
  • Application shall be accompanied by a non-refundable application fee.
  • MTOA may be extended on a written request by the consumer submitted to the nodal agency at least three months prior to such expiry. 

 

Procedure and Charges for Short Term Open Access (STOA)

  • Inter-state short term open access as per Central Electricity Regulatory Commission (Open Access in Inter-State Transmission) Regulations, 2008, or its statutory re-enactments, as amended from time to time.
  • Application seeking STOA up to four months.
  • Separate application for each month and each transaction in a month.
  • Application for STOA in any month may be up to the 15th day of the preceding month.
  • Application shall be accompanied by a non-refundable application fee.
  • Application for day-ahead open access may be submitted 3 days prior to the date of scheduling but no later than 1300 hrs of the day immediately preceding the day of scheduling.
                   

 

OTHER PROVISIONS

 

Allotment Priority

  • The allotment priority for open access in intra-state transmission system shall be as follows:
    • Distribution licensee to have highest priority irrespective of term of open access.
    • LTOA shall have priority next to the distribution licensee.
    • MTOA shall have priority next to the LTOA consumers.
    • STOA shall have priority next to the MTOA consumers.
    • Allotment priority for STOA will depend on availability of capacity.
    • Existing OA consumers to have higher priority than new OA consumers provided the existing OA consumer applies for renewal within the stipulated period prior to expiry of existing term of open access.
    • If the capacity requirement of an applicant exceeds the capacity available and the applicant is unable to restrict its capacity requirement, then the next priority consumer is considered for connection.  

Open Access Charges

Transmission Charges

  • For use of inter-state transmission system – as specified by the Central Electricity Regulatory Commission, from time to time.
  • For use of intra-state transmission system – no transmission charges shall be levied for transaction of energy generated from wind and solar sources.

 

NBPDCL (Rs./kWh)

SBPDCL (Rs./kWh)

Transmission Charges

0.51

0.51

Cross Subsidy Surcharge

Consumer Category

NBPDCL (Rs./Unit)

SBPDCL (Rs./Unit)

132 kV consumers.

1.71

1.71

33 kV consumers (other than HTSS).

1.85

1.85

11 kV consumers (other than HTSS).

1.87

1.87

HTSS consumers (33 kV and11 kV).

1.18

1.18

Wheeling Charges

Wheeling Charges

Paise/Unit

For 33 kV voltage level

27

For 11 kV voltage level

31

SLDC Charges – 0.15 Paise/kWh

 

Scheduling and Metering

Scheduling

  • Inter-state transaction – as per Central Commission specifications.
  • Intra-state transaction – as per the state grid code for consumers with load of 10 MW and above, and all generating stations irrespective of capacity.
  • Intra-state transaction – no scheduling required for capacity less than 10 MW provided the generating station from which such consumer has contracted power is subject to scheduling.

Metering

  • Special energy meters at the point of injection and drawal to be installed by the STU of the DISCOM at the cost of the customer.
  • All open access customers shall abide by the metering standards of CEA.

 

Energy Losses

Transmission Losses

  • Transmission losses for BSPTCL system for FY 2018-19 – 3.92%

Distribution Losses

NBPDCL

20%

SBPDCL

22%

Imbalance and Reactive Energy Charges

Imbalance Energy Charges

  • In case of deviation by open access consumers, the difference shall be settled at the rate determined by the Commission.
  • Payment of imbalance charges will have to be made within 10 days of issue of statement.
  • Delay in payment beyond 12 days from the date of issue of statement shall attract simple interest @ 0.04% for each day of delay.   

Reactive Energy Charges

  • 4 paise/kVAR

Link

https://berc.co.in/rules-requlations/regulations/individual-regulation

https://berc.co.in/orders/tariff/distribution/sbpdcl

https://berc.co.in/orders/tariff/distribution/nbpdcl

https://berc.co.in/orders/tariff/transmission

 

References

https://berc.co.in/orders/tariff/distribution/sbpdcl/1444-tariff-order-of-sbpdcl-for-fy-2018-19

https://berc.co.in/orders/tariff/distribution/nbpdcl/1447-tariff-order-of-nbpdcl-for-fy-2018-19

https://berc.co.in/orders/tariff/transmission/1438-tariff-order-of-bihar-state-power-transmission-co-ltd-bsptcl-for-fy-2018-19

https://berc.co.in/rules-requlations/regulations/individual-regulation/1583-terms-and-conditions-of-intra-state-open-access-regulations-2018

 

 

 

About Portal

'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More

Contact

Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India

+91 20 26613855
+91 20 26613832