Nodal Agency |
: |
Ministry of New and Renewable Energy (MNRE)
|
Applicable Technologies |
: |
|
Eligibility Conditions |
: |
For availing term loans from financial institutions, the developer should be one of the following:
|
Scheme Period |
: |
May 2018 to March 2020
|
Incentives |
: |
|
OTHER PROVISIONS |
Timeline for completion of projects |
: |
24 months from the date of sanction of assistance, with an additional six months grace period if the developer faces delays beyond his control.
|
Incentives to State Nodal Agencies |
: |
Rs.1 lakh/MW or Rs10 lakh/project whichever is less – incentives for post installation monitoring of projects and sending periodic reports to MNRE.
|
Performance Inspection |
: |
|
Monitoring of Projects |
: |
By a team comprising representatives of utilities, SNAs, experts appointed by MNRE and ministry officials.
|
Standards |
: |
Various national and international standards for equipment utilized.
|
Links |
: |
https://mnre.gov.in/node?page=9
|
References |
: |
https://mnre.gov.in/sites/default/files/schemes/scheme-Biomass-11052018.pdf
|
About Portal
'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More
About
Useful Links
Contact
Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India
+91 20 26613855
+91 20 26613832