Renewable Energy
Find latest News, Industry Updates, Markets, Finance, Policies and Regulations, Tenders
HIGHLIGHTS |
Nodal Agency |
Goa Energy Development Agency (GEDA) |
Applicable Technologies |
All renewable energy technologies. |
Policy Period |
2014 – 31st July 2024 |
Targets under Policy |
By 2020 - 50 MW solar PV and wind power, 10000 units of 100 LPD hot water equivalent of solar thermal installations, and 20 MW equivalent of biomass power generation capacity. |
Incentive Amount |
Generation-based incentives to domestic consumers installing solar roof-top projects @of Rs.3/unit for 2 years, Rs.2/unit for the next 2 years and Rs.1/unit for the following 2 years. |
Eligibility Conditions |
Solar photovoltaic plants with minimum capacity of 5 kW and solar thermal plants with minimum capacity of 100 LPD equivalent of hot water capacity. Non-solar power plants with lower limit of 5 kW. |
Tax Exemptions |
· For biomass projects, no sales tax for first seven years of production and no excise duty on production. · Electricity generated from solar power shall be exempted from electricity duty. |
Evacuation Arrangement |
Not Available |
OTHER PROVISIONS |
Use of fossil fuel |
No fossil fuel shall be allowed to be used continuously in solar thermal and biomass based projects except for initial ignition of the system or maintaining continuity of operation of generation. |
Wheeling charges within the state |
The wheeling of electricity for self use shall be allowed at 2% of the energy fed to the grid. Wheeling charges will not be applicable for captive solar generators. |
Power output |
The power output of a plant should be within plus/minus 10% of the rated capacity for the slab of every 5 years.
|
Quantum of power sale |
The quantum of power that can be injected in the grid will be allowed to exceed the statutory limit set up by JERC. |
Solar parks |
Solar power parks will be developed in order to facilitate power production from solar-based technologies. |
Promoting rooftops in public institutions |
|
Single window clearance |
The state government will facilitate and provide requisite clearances through a “Single Window Clearance Mechanism” which will be operated through GEDA. |
Links |
|
References |
http://www.indiaenvironmentportal.org.in/files/file/GEDA-SolarPower-2014.pdf |
About Portal
'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More