Renewable Energy
Find latest News, Industry Updates, Markets, Finance, Policies and Regulations, Tenders
HIGHLIGHTS |
Eligibility to seek Open Access (OA) | Consumers located in the Distribution Licensee’s area and having contracted load of 100 kVA and above, and connected to the distribution system of licensee at 11 kV and above.
| ||||||||
Electricity Tariff FY 2019-20 (Rs/kVAh) | Category | Load Factor | Energy Charges (Rs./kVAh) | Fixed/Demand Charge per Month | |||||
Contract load up to 1000 kVA | Up to 40% | 3.95 | Rs.300/kVA of the billable demand* | ||||||
Above 40% | 4.35 | ||||||||
Contract load above 1000 kVA | Up to 40% | 3.95 | Rs.360/kVA of the billable demand* | ||||||
Above 40% | 4.35 | ||||||||
*Billable demand shall be the actual maximum demand or 80% of the contracted load, whichever is higher.
| |||||||||
Connectivity Charges and Procedure | Renewable Energy Generators
Connectivity to Intra-state Transmission System
Connectivity to Distribution System
Connectivity to Distribution System by a Consumer of Distribution Licensee As per the UERC (Release of New HT and EHT Connections, Enhancements and Reduction of Load) Regulations, 2008.
|
| |||||||
Nodal Agency | As in Table below | ||||||||
Procedure and Charges for Long Term Open Access (LTOA) |
| ||||||||
Location of Injection and Drawal Point | Nodal Agency | Application Fee (Rs.) | Time Frame for Processing the Application | ||||||
Both within the same Distribution Licensee’s area. | Distribution Licensee | 50,000 | 20 days | ||||||
Drawal point in distribution system and injection point in intra-state transmission system (and vice-versa). Both in intra-state transmission system. | STU
| 2,00,000 | 120 days where T&D system augmentation is not required. Where required: 270 days for transmission system, 180 days for distribution system. | ||||||
In different states | CTU | CERC regulations | CERC regulations | ||||||
Without involving Inter-state Transmission System Bank Guarantee of Rs.10,000/- per MW of the total power transacted, drawn in favour of Nodal Agency and kept valid till execution of LTOA agreement.
| |||||||||
Procedure and Charges for Medium Term Open Access (MTOA) |
| ||||||||
Location of Injection and Drawal Point | Nodal Agency | Application Fee (Rs.) | Time Frame for Processing the Application | ||||||
Both within the same Distribution Licensee’s area. | Distribution Licensee | 50,000 | 20 days | ||||||
Drawal point in distribution system and injection point in intra-state transmission system (and vice-versa). | STU | 1,00,000 | 40 days | ||||||
Both in intra-state transmission system. | 20 days | ||||||||
In different states. | CTU | CERC regulations | CERC regulations | ||||||
Without involving Inter-state Transmission System Start date of MTOA shall not be earlier than 5 months and not later than 1 year from the last day of the month in which application was made.
| |||||||||
Procedure and Charges for Short Term Open Access (STOA) |
| ||||||||
Location of Injection and Drawal Point | Nodal Agency | Application fee (Rs.) | Time Frame for Processing Application | ||||||
Both within the same Distribution Licensee’s area. | Distribution Licensee | 2000
| 7 working days if applying for the first time; otherwise 3 working days. | ||||||
Drawal point in distribution system and injection point in intra-state transmission system (and vice-versa). Both in intra-state transmission system. | SLDC | 5000 | |||||||
In different states | RLDC of consumer | CERC regulations | CERC regulations | ||||||
Without involving Inter-state Transmission System
|
OTHER PROVISIONS |
Allotment Priority |
|
Open Access Charges | Transmission Charges
Cross Subsidy Surcharge
Wheeling Charges
|
Scheduling and Metering | Scheduling
Metering
|
Energy Losses | Transmission Losses Intra-state transmission losses (approved) – 1.40% (MYT FY 2019-20 to 2021-22).
Distribution Losses Distribution losses considered for OA – 14.25% (FY 2019-20).
|
Imbalance/ Deviation and Reactive Energy Charges | Deviation Energy Charges
Reactive Energy Charges In accordance with the IGEC and State Grid Code.
|
Links | http://www.uerc.gov.in/Rules%20and%20regulation/UERCRegulations/UERC%20Current%20Regulations.html
|
References | UERC (Terms & Conditions of Intra State Open Access) Regulations, 2015 Uttarakhand Electricity Regulatory Commission (Terms and Conditions of Intra-State Open Access) (First Amendment) Regulations, 2016. Uttarakhand Electricity Regulatory Commission (Terms and Conditions of Intra-State Open Access) (Second Amendment) Regulations, 2018 ARR for FY 2019-20 for Uttarakhand Power Corporation Ltd. ARR for FY 2019-20 for PTCUL Ltd. ARR for FY 2019-20 for SLDC. |
About Portal
'All About Renewables' aims to bring about a change in the way we 'look and search' for data on renewables today, by providing access to the latest developments in the renewable energy sector (specifically renewable electricity), along with cross-linkages to the conventional energy sector, all on one single platform... Read More
About
Useful Links
Contact
Plot No.44, Hindustan Estates,
Kalyani Nagar, Pune 411 006, India
+91 20 26613855
+91 20 26613832